Yisen Carpet completed the delivery of a banquet hall project for a five-star InterContinental Hotel

When we took on this project in the middle of last year, to be honest, my first reaction was not excitement but nervousness. A banquet hall at an InterContinental hotel in a coastal city, 780㎡ in area, with a modern light luxury + ocean-inspired design style, required the carpet not only to handle multiple scenarios such as banquets, meetings, and weddings, but also to withstand scrutiny from the group executives and the media at the opening ceremony — and the schedule was only 52 days, from sampling to installation.

Final delivery result: completed 2 days ahead of schedule, passed inspection on the first try, and the client’s project director wrote four words on the acceptance form — ”beyond expectations.”

Today I’m going to break down the entire project process. This isn’t to show off, but to let peers and clients see: behind the delivery of a high-quality hotel carpet project, there are far more steps than most people imagine.


1. Project background: why we dared to take on this order

First, let’s go over the key project metrics:

Project parameters Requirements
Project positioning Five-star InterContinental brand, opening ceremony venue
Area Banquet hall main hall 780㎡ + foyer 260㎡ = 1040㎡
Design style Modern light luxury + ocean wave elements
Craft requirements Hand-tufted (custom pattern)
Material requirements 80% New Zealand wool + 20% nylon 66 blend
Flame retardant rating GB 8624 B1 level
Schedule requirement 52 days (including sampling, production, logistics, and installation)
Delivery standard Seamless splicing, first inspection pass

For a 1040㎡ custom hand-tufted carpet project to be completed in 52 days, the standard lead time in the industry is usually 70–80 days. So why did we dare accept it?

Because we had an ace up our sleeve: our factory base in the Pearl River Delta had always kept flexible sampling and production line scheduling, and our core hand-tufting team of 36 people was all on site, so we could fully support the capacity. At the same time, we made it clear to the client that 52 days was feasible, but design revisions during the sampling stage had to be limited to no more than 2 rounds; beyond that, there simply wouldn’t be enough time.

There’s a very true saying in projects: the prerequisite for making a promise is that you know your own factory inside and out. From yarn procurement, dyeing and material preparation, to backing fabric inventory and craftsmen scheduling, every step had already been synchronized with production before we even accepted the order.


2. From design draft to sampling: the most painful 17 days

In the original plan from the designer, the main pattern in the banquet hall was interwoven waves in three different shades of blue, forming a gradient from light to dark from the entrance to the stage. It sounded simple, but after we received the drawings, we found three problems:

1️⃣ Three shades of blue + gradient transition require11 color levels; each level needs to be tufted separately

2️⃣ The staggered boundary of the waves is not a straight line, but an irregular curve, so when tufting, the master needs to make on-site judgment of the transition points

3️⃣ The 780㎡ scheme needs to be divided into6 piecesfor splicing, and the pattern splicing alignment accuracy must be controlled within ±1mm

The proofing stage went through two rounds. In the first round of proofing, the ”stepped” feeling in the gradient transition area was too obvious — a visible color-step boundary appeared on the transition band between two adjacent color numbers. The solution proposed by the process team was to introduce ”intermediate transition color” yarn in the transition area, changing the original two-color boundary into a three-color mixed transition. This adjustment increased the number of color layers from 11 to 14, but improved the smoothness of the transition to a perceptible degree.

The second round of proofing satisfied the client very much, and they signed off directly. From receiving the design to finalizing the version,it took 17 days— 2 days longer than the planned 15 days, but the later production stage made up for it.

💡 Tip: For custom pattern projects, it is recommended to carry out the proofing stage at the factory, not in the showroom. The lighting in the showroom is completely different from the actual lighting in the banquet hall (usually a mix of large-area LED and natural light), so the same color may appear 3-5 shades cooler or warmer under different lighting.


3. Production stage: 36 people, 27 days, 1040㎡

After the proof is approved, mass production begins, which is the most demanding part of the entire project.

Key process points:

  • Tufting density:50 stitches/square foot(Standard handmade tufting in five-star hotels is usually 40-45 stitches; because this project had high requirements for gradient accuracy in the pattern, it was increased by one level)
  • Yarn blend: New Zealand wool and nylon 66 in a80:20 ratiopre-mixed and then tufted, ensuring a handmade texture while improving wear resistance
  • Flame-retardant solution: the cotton backing usesdouble-sided flame-retardant spraying + flame-retardant latex coating; the inspection report issued by SGS shows that the critical heat flux reaches7.2 kW/m²far above the B1-level bottom line of 4.5 kW/m²

The 36 tufting мастers were divided into 6 groups, with each group responsible for 1 piece (each piece is about 130-170㎡). After each piece is completed, the quality inspection team conductsthree-way joint inspectionThe pile height deviation is controlled within ±0.5 mm, the pattern seam marking error does not exceed ±1 mm, and the uniformity of the backing adhesive thickness is no less than 95% of the standard value.

There is an easily overlooked detail in hand-tufted projects:the temperature and humidity control of the production environment for each piece. Yarn has different elasticity and elongation rates under different humidity levels. If 6 carpets are completed under different humidity conditions, the final installed carpets may have inconsistent dimensions. Our approach is to keep the workshop temperature and humidity constant during production,at 22±2°C and 55±5% humidity,ensuring that each piece is completed in the same environment.


IV. Logistics and installation: a risk stage that is usually underestimated

After carpet production is completed, only 70% of the work is done. The remaining 30% lies in logistics and installation.

The finished product of this 1040㎡ hand-tufted carpet weighs approximately3.2 tonsand is transported in 6 rolls. Each roll is about 4 meters wide, with lengths ranging from 30 to 50 meters. There are two things we worry about most during transportation:moisture and compression deformation

The packaging plan is: each roll of carpet is first wrapped withwaterproof breathable film, then protected with bubble wrap, and finally sealed with woven bags on the outermost layer. Moisture-proof packs are placed at both ends of each roll. During loading, the rolls are stood upright and must not be stacked or compressed.

For the installation stage, Yisen sent its own installation team to the site, 4 people, and it took3 daysto complete all installation and edge finishing. During installation, an on-site issue was encountered—the maximum deviation in the levelness of the banquet hall floor was5 mm, which, although within the tolerance range for carpet installation, would affect the feel underfoot and the visual flatness. Our installation team used self-leveling repair mortar to locally level areas with deviations exceeding 3 mm, spending an extra half day, but ensuring the final pile surface was perfectly flat.


V. After delivery: customer feedback and project review

On the day of acceptance, more than a dozen people from the client side came—owner representatives, the hotel engineering director, design representatives, and the regional operations director of the InterContinental Group. They walked back and forth on the carpet several times, crouched down to feel the seams, and used a high-powered flashlight with side lighting to check the uniformity of the pile surface.

Acceptance result:Passed on the first try, with no items for rectification.

Later, the engineering director said something at the project review meeting that left a deep impression on me: ”The three things I was worried about before—color deviation, visible seams, and uneven pile—did not appear at all. Your delivery standard would also rank in the first tier within the InterContinental system.”

Project follow-up visit (6 months later): At the beginning of this year, we conducted a routine follow-up visit. The hotel had already hosted more than 40 banquets and conference events. Feedback from the banquet hall manager was: it had been cleaned 3 times (dry-foam cleaning), and the pile remained in good condition, with no issues such as pile reversal, pilling, or color differences.


VI. Review: what did this project teach us

After each project is completed, we conduct an internal review. This project is especially worth recording:

What was done well:

  • Production scheduling had already reserved15% of flexibilityto address a 2-day delay in sampling during actual production
  • During the sampling stage, we insisted on doingtwo roundsand did not skip the second round of confirmation in order to meet the deadline
  • The installation team’s on-site issue anticipation ability—proactively handled the floor flatness issue without waiting for the client to discover it

What could be done better:

  • The waterproof protective layer in the packaging plan could use one more layer. We encountered rainy weather during logistics; although no damage was caused, we should be more cautious
  • There was some friction early in the project with the design team over aligning color language. Next time, it is recommended to hold a ”color expectation alignment meeting” before sampling, comparing the design renderings and the actual yarn color swatches under the same light source

The most valuable takeaway for us: It proved that Yisen Carpet, in the field of high-end custom hand-tufted carpets, already has complete delivery capabilities—from design collaboration, sample confirmation, and scaled production to on-site installation. What clients really pay for is control across the entire chain.


If you want to learn more about the execution details of this project, or see the specific sampling comparison photos and installation site records, you can directly contact the Yisen Carpet project team. We archive every project we do—not the version shown to clients, but the real records we use for internal review.